31 8월 2011 Avatara 2 Condominium - progress report Report date - August 30, 2011
° Topping 6th floor ready
° Columns from 6th floor ready
° Beams 7th floor formwork started
° Main stair structure 1st floor to 5th floor ready
° Fire stair structure 1st floor to 5th floor ready